Splash247: Genoa port expansion advances with breakwater milestone

Published by Splash247

Italian construction group Webuild has completed seabed consolidation work for the new Genoa breakwater, marking another milestone in one of Europe’s largest maritime infrastructure projects.

The work, carried out by the Webuild-led PerGenova Breakwater Consortium on behalf of the Western Ligurian Sea Port Authority, involved installing approximately 67,300 gravel columns to stabilise nearly 300,000 sq m of seabed.

The columns, extending more than 722 km in total, were installed using a technique known as Wet Top Feed, which employs vibrating probes to deposit and compact gravel beneath the seabed.

Around 2.8m tonnes of gravel were used, with individual columns measuring between 6 and 13.5 m in length and at least 1.1 m in diameter. Offshore operations involved three specialised pontoons and eight cranes working simultaneously around the clock.

Meanwhile, construction of the breakwater itself continues, with the latest concrete caisson installation taking the structure beyond 1,700 metres in length. The project currently employs approximately 800 workers and involves more than 400 direct suppliers.

In October, Webuild reported that the breakwater had reached 1,630 m following another caisson installation. Once completed, the new infrastructure will allow the Port of Genoa to accommodate the latest generation of large container ships, improving access to one of the Mediterranean’s busiest shipping gateways.